Barratt East London contract opportunities at The Lanes (Parcel 1)
On this page
Barratt East London is advertising the following contract opportunities for development works at The Lanes (parcel 1).
Requirements
The successful contractor will need to complete Barratt East London's pre-assessment questionnaire to become an approved supply chain member.
Other requirements:
- Public liability/employers insurance
- Company details to be provided
- Health and safety policy to be provided
- Trade-specific accreditations
- CSCS cards for relevant roles
Opportunities
Find out more about specific opportunities.
| Package | Scope | Value | Out to tender | Start on site | Anticipated completion |
|---|---|---|---|---|---|
| Floor and wall tiling - Block A | Supply and install ceramic floor and wall tiling | £92,000 | 17/06/26 | 21/10/26 | 27/11/26 |
| Paint and decorate - Block A | Supply and install all painting and decorating | £198,000 | 28/05/26 | 01/10/26 | 16/12/26 |
| Floor finishes - Block A | Supply and install carpets, vinyl and other floor finishes | £374,000 | 14/05/26 | 01/10/26 | 27/11/26 |
| Mastic – Blocks A and B | Supply and install internal mastic | £41,600 | 17/06/26 | 23/09/26 | 27/01/27 |
| Builders clean - Blocks A and B | Builders clean works to communal areas and apartments | £90,400 | 25/05/26 | 28/09/26 | 27/01/27 |
| Hard landscaping | Supply and install hard landscaping to courtyards, parkland, play areas, roadways and paving | £748,000 | 22/05/26 | 07/10/26 | 02/12/26 |
| Soft landscaping | Supply and install soft landscaping to courtyards, parkland, play areas, roadways and paving | £329,000 | 22/05/26 | 07/10/26 | 02/12/26 |
How to apply
To express interest in an opportunity, contact:
- Jude Benson-Ryal - jude.benson-ryal@barrattlondon.com
- Jamie Burridge - jamie.burridge@barrattlondon.com